BUYING GUIDE · PLANNING

Minimum Order Quantity & Lead Times

Capital equipment doesn't work like a component order — there's no MOQ in the traditional sense, but timeline planning still matters. Here's what to expect.

Minimum Order Quantity

We accept single-unit press orders — there is no minimum press quantity. For spare parts and consumable tooling components, small-quantity orders are accepted, though per-unit pricing improves at higher quantities for parts we don't keep in standard stock.

What Affects Lead Time

  • Standard platform vs. custom configuration (custom builds add engineering time upfront)
  • Whether die design and build is bundled with the press order
  • Current production schedule load at the time of order
  • Speed of drawing approval and deposit confirmation on your end

Typical Lead Times

Standard Press (Stock Config)
10–14 Weeks
Standard Press + Die Design
14–18 Weeks
Custom/OEM Configuration
16–22 Weeks
Spare Parts (Stocked)
1–2 Weeks
Spare Parts (Made-to-Order)
3–6 Weeks

How to Compress the Timeline

  • Send a complete part drawing and specification upfront — incomplete information is the most common source of delay
  • Confirm deposit payment promptly once the quotation is agreed
  • Decide on control-platform language and voltage/frequency requirements early
  • If die design is bundled, respond quickly to DFM feedback and tryout sample approval requests

Working against a launch date?

Tell us your target production start date — we'll confirm whether it's achievable and what would need to happen to hit it.